Crane infill for hi-rise project 

Project Details

Sector:
Commercial
Client:
Cara Flooring
Pump Used:
31HT Telescopic Truck Mounted Concrete Pump

Crane infill for hi-rise project 

We were recently involved in the construction of a commercial building in the centre of Manchester.

After the removal of the tower crane,  we were instructed to install a vertical riser through the centre of the building to the top floor.

Once constructed, we pumped a steel fibre concrete mix to the top floor, breaking down the pipeline and removing it as we came down the building.

All 14 floors were completed in one day.